Building Sylvania Twp.'s fire station No. 1

Operations at Firehouse No. 1 are just months away with a bulk of the construction project completed. More than 22,000 blocks have been laid and cemented together for the frame and facade of the Sylvania Township firehouse on Monroe Street. CLICK ANY IMAGE TO VIEW FULL PHOTO, START SLIDE SHOW.

The Sylvania Township Fire Department's fire station No. 1 is on track to be completed by November first, says Mosser Construction, Inc. superintendent Dan Schroeder, despite three weeks of rain early in the summer. Enlarge | Buy This Photo The Sylvania Township Fire Department's fire station No. 1 is on track to be completed by November first, says Mosser ...
THE BLADE/JETTA FRASER
Sylvania Township Fire Chief Jeff Kowalski discusses the progress of the township’s new fire station and points out its features. Enlarge | Buy This Photo Sylvania Township Fire Chief Jeff Kowalski discusses the progress of the township’s new fire station and points out its features....
THE BLADE/JETTA FRASER
When finished, the fire station's pole will be in this area, where the ladder is placed. Enlarge | Buy This Photo When finished, the fire station's pole will be in this area, where the ladder is placed.
THE BLADE/JETTA FRASER
Steps to the second floor of Sylvania Township Fire Station No. 1 will be built here. In the previous fire station, a person had to duck to avoid hitting the ceiling on the way down the stairs. Enlarge | Buy This Photo Steps to the second floor of Sylvania Township Fire Station No. 1 will be built here. In the previous fire ...
THE BLADE/JETTA FRASER
Tom Kohler, of Gibsonburg, a carpenter foreman, at the ladder to the second floor. The ladder will be replaced by a fire pole. Enlarge | Buy This Photo Tom Kohler, of Gibsonburg, a carpenter foreman, at the ladder to the second floor. The ladder will be replaced by ...
THE BLADE/JETTA FRASER